Case Study –
Ar. Prashant Soni
August 2022
Near Hari Champa, Adajan, Surat
Background
Challanges
Existing Damage: Bubbles on paint and water seepage affecting adjacent walls and staircase.
Client Requirement: Ensuring the bathroom flooring remained intact during the waterproofing process.
Time Constraint: Completing the project within a week.
Solution
After a thorough inspection, our team decided to use Tapik’s flexible waterproof 3-component mortar for corner joint filling. This solution was chosen for its flexibility and effectiveness in sealing joints without requiring extensive demolition or damage to the existing flooring.
- Surface Preparation:
- Cleaned the affected areas to remove any loose paint and debris.
- Ensured the surfaces were dry and free from contaminants.
- Application of Waterproofing Solution:
- Applied Tapik’s flexible waterproof 3-component mortar to the corner joints and areas showing signs of seepage.
- Ensured thorough coverage and proper sealing of all joints and cracks.
- Final Inspection:
- Conducted a water leakage test to confirm the effectiveness of the waterproofing solution.
- Monitored the treated areas for a few days to ensure no further seepage occurred.
Client’s feedback and Conclusion
Ar. Prashant Soni expressed his satisfaction with the project, noting the professionalism and efficiency of our team. He was particularly pleased that the solution did not require any damage to the existing bathroom flooring and effectively resolved the water seepage issue.
This case study highlights our ability to provide effective and client-specific waterproofing solutions. By using advanced materials and techniques, we were able to deliver a durable and non-invasive solution for the old bathroom in the residential bungalow near Hari Champa, Adajan, Surat, Gujarat.